VIRTUAL CAIM
Compliance audit

ISO/IEC 27001:2022 and
DPDP Readiness Audit

Prepared for Example Finserv Ltd. (fictional client). Independent readiness audit of the information security management system and personal data protection practices.
SAMPLE REPORT - fictional engagement, sanitized
Report ID
VC-SAMPLE-CMP-2026-001
Client
Example Finserv Ltd. (fictional NBFC)
Audit dates
Stage-1 style document review 5 to 9 October 2026; on-site and technical sampling 12 to 23 October 2026
Report date / version
30 October 2026 / v1.0 (Final)
Nature of audit
Pre-certification readiness audit. Not a certification audit.
Classification
Confidential (sample). Fictional data throughout.

Document control

Audit criteria
ISO/IEC 27001:2022 including Amendment 1:2024; Statement of Applicability v3.2; Digital Personal Data Protection Act, 2023 and the Rules as notified; client policies
Audit team
Lead Auditor, 2 Auditors, 1 technical expert (names and credentials in the audit plan, sample)
Independent reviewer
One reviewer, not part of the audit team (sample)
Distribution
CISO and ISMS Manager. Shared from an official mailbox through an encrypted channel.
Draft and final dates
Draft 27 October 2026, final 30 October 2026

Version history

VersionDateStatusDescription
0.116 Oct 2026DraftInterim note of Major nonconformity shared with CISO at the end of fieldwork week 1
0.927 Oct 2026DraftFull draft for factual accuracy
1.030 Oct 2026FinalIssued

Contents

  1. 1. Executive summary3
  2. 2. Scope, criteria and approach4
  3. 3. Management system conformity (clauses 4 to 10)5
  4. 4. Annex A control conformity (selected controls)7
  5. 5. Nonconformities and corrective action plan8
  6. 6. DPDP Act readiness11
  7. 7. Certification-readiness verdict13
  8. 8. Roadmap13
  9. Annex A. Evidence register14
  10. Annex B. Glossary14
  11. Annex C. Sign-off14
Important noteThis is a readiness audit by Virtual Caim. It is not an ISO/IEC 27001 certificate. Certification is granted by an accredited certification body after its own Stage 1 and Stage 2 audits. A readiness audit tells you how likely that outcome is and what to fix first.

1. Executive summary

Example Finserv has a working ISMS with real strengths: committed leadership, a sound risk method, good technical controls and a responsive security team. Most gaps are about evidence, testing and keeping records current. One Major nonconformity (internal audit) must be closed before a certification body visits.

1
Major nonconformity
NC-01, internal audit
4
Minor nonconformities
NC-02 to NC-05
10
Observations
improvement opportunities
50%
DPDP readiness
weighted over assessable obligations

Of the 25 clause areas assessed, 15 conform fully, 8 conform with observations, 1 carries a minor nonconformity and 1 a major nonconformity. Of the 33 Annex A controls sampled, 19 conform fully.

Strengths

What needs attention

Verdict in one lineCONDITIONALLY READY. Ready for a certification body Stage 1 after NC-01 and NC-02 are closed, and for Stage 2 after NC-03 to NC-05 are closed and one full management review cycle has used the corrected inputs. Estimated 10 to 12 weeks.

2. Scope, criteria and approach

2.1 Audit scope and objectives

2.2 Criteria

CriteriaVersionUse
ISO/IEC 27001:2022 with Amendment 1:20242022 and 2024Clauses 4 to 10 and Annex A
Statement of Applicabilityv3.2Control selection and status
Digital Personal Data Protection Act, 20232023Obligations of Data Fiduciaries, rights of Data Principals
DPDP Rules, 2025Nov 2025Procedural detail, phased commencement
CERT-In Directions28 Apr 2022Logging, time synchronisation, incident reporting
Client policies and proceduresCurrentInternal requirements

2.3 Approach and sampling

MethodWhat we didSample
Document reviewPolicies, procedures, registers, records63 documents
InterviewsTop management, ISMS manager, control and process owners, HR, procurement, IT22 people
ObservationOperational practice, physical areas, SOC dashboard6 walkthroughs
Technical samplingConfiguration checks on logging, retention, NTP, access, backup, TLS22 log sources, 20 change records, 25 leavers, 10 supplier contracts, 8 releases
Evidence testingRe-performance of reviews and approvalsPer control

Sampling followed a risk-based approach: higher criticality systems and processes were sampled more heavily. Sample sizes are stated in the evidence for each finding. Audit time was 24 auditor-days over 2 weeks.

2.4 Classification of results

ResultMeaning
ConformsRequirement met with objective evidence
ObservationMet, but an improvement opportunity or an early risk was noted
Minor NCA requirement is not fully met; isolated or limited lapse. Corrective action required
Major NCRequirement not met, or a systemic failure that undermines the ISMS or its ability to achieve intended outcomes. Corrective action required before certification
N/ANot applicable or not yet in force

2.5 Limitations

3. Management system conformity (clauses 4 to 10)

ClauseRequirementEvidence examined and resultResult
4.1Understanding the organisation and its contextContext register reviewed (v2.1, dated Mar 2026), covers regulatory, technology and market issues. Climate change considered as a relevant issue as required by Amendment 1:2024; record present.Conforms
4.2Needs and expectations of interested partiesInterested-party register lists regulators (RBI, CERT-In, DPB), customers, partners, DSAs, auditors. Requirements mapped. Climate-related requirements assessed.Conforms
4.3Scope of the ISMSScope statement covers lending platform, back-office and supporting infrastructure at two locations. One cloud service and DSA portal described as boundary interfaces.Conforms
4.4ISMS and its processesProcess map available; interactions defined. Two process owners were unable to explain inputs and outputs.Observation
5.1Leadership and commitmentBoard minutes show approval of the policy and budget; CISO reports quarterly.Conforms
5.2Information security policyPolicy v4.0 approved and communicated. Staff interviews (9 of 9) aware of the policy.Conforms
5.3Roles, responsibilities and authoritiesRACI in place for CISO, ISMS manager, asset and risk owners. Deputy for CISO not formally named.Observation
6.1.1Actions to address risks and opportunitiesRisk methodology and criteria documented, aligned to enterprise risk appetite.Conforms
6.1.2Information security risk assessmentRisk register covers 64 assets and 118 risks; assessed in January 2026. Repeatable scoring method in use.Conforms
6.1.3Information security risk treatmentTreatment plan approved. Statement of Applicability (v3.2) lists all 93 controls, but 14 inclusion or exclusion decisions have no rationale and 6 controls are marked implemented without evidence reference.Minor NC
6.2Information security objectives and planning to achieve them9 objectives, measurable, owners and dates assigned, tracked quarterly.Conforms
6.3Planning of changesChange procedure refers to ISMS impact. Two of five sampled changes lacked ISMS impact notes (introduced as a clause by Amendment 1:2024).Observation
7.1ResourcesSecurity budget approved; tooling in place.Conforms
7.2CompetenceCompetence matrix and training records for ISMS roles. 3 of 12 certificates expired.Observation
7.3AwarenessInduction and annual training; completion 91% (target 95%).Observation
7.4CommunicationCommunication plan defines what, when, whom and how. Evidence of use present.Conforms
7.5Documented informationDocument control system in place, version history intact, access controlled.Conforms
8.1Operational planning and controlOperational controls documented; outsourced processes identified (SOC, cloud).Conforms
8.2Information security risk assessment (operation)Risk assessment repeated after the platform release in June 2026.Conforms
8.3Information security risk treatment (operation)Treatment plan tracked monthly; 79% actions closed against schedule.Conforms
9.1Monitoring, measurement, analysis and evaluationMetrics defined for 9 objectives; 7 reported quarterly, 2 not reported in Q2.Observation
9.2Internal auditAudit programme exists but the technology controls (Annex A.8) and the disaster recovery site were not audited in the last 12 months. Auditor independence not evidenced for two audits. See NC-01.Major NC
9.3Management reviewReviews held in Feb and Aug 2026 with required agenda items. Inputs lacked internal audit results (see NC-01).Observation
10.1Continual improvementImprovement log with 22 entries, 15 closed.Conforms
10.2Nonconformity and corrective actionCorrective action procedure followed for 11 of 12 sampled incidents; root cause recorded in 9.Observation

4. Annex A control conformity (selected controls)

The 93 controls of Annex A are grouped into organisational (37), people (8), physical (14) and technological (34) themes. We sampled the controls most relevant to a lending business and the risks in the risk register. Controls not listed were reviewed through the SoA only.

ControlTitleEvidence examined and resultResult
A.5.1Policies for information securityPolicy set reviewed annually; approved by management.Conforms
A.5.7Threat intelligenceSubscription to CERT-In advisories and a commercial feed; monthly review recorded.Conforms
A.5.9Inventory of information and other associated assetsAsset register covers 94% of sampled items. Cloud assets reconciled quarterly.Observation
A.5.15Access controlAccess control policy in place; role matrix for lending platform reviewed.Conforms
A.5.16Identity managementJoiner, mover, leaver process followed for 24 of 25 sampled leavers within 24 hours.Observation
A.5.18Access rightsQuarterly access reviews performed for 3 of 4 critical systems; the DSA portal review was skipped in Q2.Observation
A.5.19Information security in supplier relationshipsSupplier policy exists. 6 of 25 critical suppliers lack a security assessment on file. See NC-05.Minor NC
A.5.23Information security for use of cloud servicesCloud shared-responsibility matrix documented; configuration reviews quarterly.Conforms
A.5.24Incident management planning and preparationIncident response plan v3.0, roles named, tested by tabletop in April 2026.Conforms
A.5.26Response to information security incidents5 of 5 sampled incidents handled per procedure, with lessons learned.Conforms
A.5.29Information security during disruptionBCP security requirements included. Alternate site controls reviewed.Conforms
A.5.30ICT readiness for business continuityDisaster recovery test for the core lending system not performed in the last 12 months. See NC-03.Minor NC
A.5.31Legal, statutory, regulatory and contractual requirementsRegister includes IT Act, CERT-In Directions, RBI directions, DPDP Act. Owner assigned.Conforms
A.5.34Privacy and protection of PIIPrivacy policy and notice exist. No record of processing activities that maps to DPDP requirements. See section 6.Observation
A.6.3Information security awareness, education and trainingPhishing simulation conducted quarterly; click rate 6.2%, down from 9.8%.Conforms
A.6.8Information security event reportingStaff know the reporting channel. 214 reports in 12 months.Conforms
A.7.2Physical entryBadge access logs reviewed monthly at the data centre; visitor logs complete.Conforms
A.7.4Physical security monitoringCCTV retention is 30 days. Policy asks for 90 days.Observation
A.8.1User endpoint devicesEndpoint standard enforced through MDM on 97% of devices.Conforms
A.8.2Privileged access rightsPrivileged access managed through a vault with approval and session recording. 2 dormant admin accounts found.Observation
A.8.5Secure authenticationMFA enforced for remote access and administrators. Legacy authentication still allowed on one protocol.Observation
A.8.7Protection against malwareEDR on 98% of endpoints; email gateway sandboxing active.Conforms
A.8.8Management of technical vulnerabilitiesMonthly scans, annual penetration test by an empanelled auditor. Critical patches closed within SLA in 19 of 21 cases.Observation
A.8.9Configuration managementHardening baselines exist for operating systems and databases; drift checks monthly.Conforms
A.8.13Information backupBackups run daily with success monitoring. Restore test for the core lending database not evidenced for the last 12 months. See NC-03.Minor NC
A.8.15LoggingLogs centralised in SIEM. Retention is 90 days for 6 of 22 sampled sources, against the organisation's own 180 day requirement. See NC-04.Minor NC
A.8.16Monitoring activities24x7 monitoring by an external SOC; monthly reports reviewed.Conforms
A.8.20Networks securitySegmentation between corporate, production and DSA zones verified on firewall rules.Conforms
A.8.24Use of cryptographyCryptography standard in place; TLS 1.2 or above on tested services; key management procedure documented.Conforms
A.8.25Secure development life cycleSDLC policy with security gates. Security sign-off recorded for 7 of 8 sampled releases.Observation
A.8.28Secure codingSecure coding guidelines issued; static analysis in the pipeline for two of five repositories.Observation
A.8.29Security testing in development and acceptancePre-release VAPT performed for all internet-facing releases in the last 12 months.Conforms
A.8.32Change managementChange records sampled (n=20) show approvals and rollback plans. One emergency change closed late.Conforms

Summary of 33 sampled controls: 19 conform, 10 conform with observations, 4 minor nonconformities (NC-02 to NC-05 in part), 0 major.

5. Nonconformities and corrective action plan

Each nonconformity is stated against the requirement, supported by evidence and root cause analysis, and paired with a corrective action plan. Closure will be verified by Virtual Caim before the certification body is booked.

NC-01 Clause 9.2 Internal audit  Major NC

Requirement
The organisation shall conduct internal audits at planned intervals (clause 9.2.1) and plan, establish, implement and maintain an audit programme covering all in-scope processes (9.2.2).
Evidence
The 2026 audit programme lists 14 audits. 9 were completed. The technology controls (Annex A.8) and the disaster recovery site were not audited. Internal audit report IA-2026-04 was signed by the process owner who also owned the audited process (objectivity not evidenced). Management review of August 2026 did not receive audit results as an input.
Root cause
Audit planning relied on the ISMS manager's availability, and no back-up auditor was trained. No tracker flagged slipping audits to top management.
Corrective action plan
1. Appoint and train two additional internal auditors, one of them from outside the IT function. 2. Re-baseline the programme with a monthly tracker reported to the CISO. 3. Complete the A.8 and DR site audits. 4. Add audit results to the management review input checklist.
Owner / due
ISMS manager / 45 days
Verification
Re-audit evidence and updated programme

NC-02 Clause 6.1.3(d) Statement of Applicability  Minor NC

Requirement
The organisation shall produce a Statement of Applicability with the necessary controls, justification for inclusion, whether implemented, and justification for exclusions of Annex A controls.
Evidence
SoA v3.2: 14 of 93 controls have no inclusion or exclusion rationale. 6 controls are marked Implemented without an evidence reference.
Root cause
SoA was updated by copying the 2013 mapping and not reviewed line by line after the 2022 transition.
Corrective action plan
1. Review all 93 controls with control owners. 2. Record rationale and evidence for each. 3. Approve SoA v3.3 through management review.
Owner / due
CISO / 30 days
Verification
SoA v3.3 sampled by auditor

NC-03 Annex A.8.13 Information backup and A.5.30 ICT readiness for business continuity  Minor NC

Requirement
Backup copies shall be tested regularly (A.8.13). ICT readiness shall be planned, implemented, maintained and tested (A.5.30).
Evidence
No restore test evidence for the core lending database in the last 12 months. Last disaster recovery failover test dated September 2025. Recovery time objective is 4 hours; no evidence it was met.
Root cause
Test schedule depended on a business freeze that was repeatedly postponed.
Corrective action plan
1. Run a restore test within 30 days and record time taken. 2. Schedule a DR failover test with business sign-off for Q1. 3. Record results against the RTO and RPO in the BCP.
Owner / due
Head of IT / 30 days (restore), 90 days (DR)
Verification
Test reports with timings

NC-04 Annex A.8.15 Logging  Minor NC

Requirement
Logs recording activities, exceptions, faults and relevant events shall be produced, stored, protected and analysed. The organisation's own policy sets 180 days of retention, in line with the CERT-In Directions of 28 April 2022.
Evidence
6 of 22 sampled log sources keep 90 days (legacy ERP, three branch devices, two application servers). NTP source for two branch routers could not be shown to trace to NIC or NPL servers.
Root cause
Retention was configured per system at deployment and not reviewed against the 2022 Directions.
Corrective action plan
1. Raise retention to 180 days and confirm storage within India. 2. Standardise NTP to the corporate source traceable to NIC or NPL. 3. Add retention and NTP checks to the monthly control review.
Owner / due
Head of IT, SOC lead / 30 days
Verification
Configuration screenshots, SIEM retention report

NC-05 Annex A.5.19 and A.5.20 Supplier relationships  Minor NC

Requirement
Processes shall be defined and implemented to manage the information security risks of the use of suppliers, and relevant requirements shall be agreed in supplier agreements.
Evidence
6 of 25 critical suppliers have no security assessment on file. 4 of 10 sampled contracts do not include breach notification timelines or data return and deletion terms.
Root cause
Supplier assessments were done at onboarding only and the template predates the DPDP Act.
Corrective action plan
1. Complete assessments for the 6 suppliers. 2. Adopt a contract security and data protection schedule with breach notification timelines. 3. Review critical suppliers annually.
Owner / due
Procurement and CISO / 60 days
Verification
Assessment reports, signed addenda

Observations and opportunities for improvement

RefObservationSuggestion
OFI-01Process owners unable to explain inputs and outputs (4.4)Brief owners and add process map to induction
OFI-02Deputy for CISO not named (5.3)Name a deputy
OFI-033 of 12 competence certificates expired (7.2)Renewal tracker
OFI-04Awareness completion 91% (7.3)Escalate to managers monthly
OFI-05Two objectives not reported in Q2 (9.1)Add to dashboard
OFI-06Two dormant admin accounts (A.8.2)Disable and add monthly check
OFI-07Legacy authentication allowed on one protocol (A.8.5)Disable after impact check
OFI-08Static analysis on two of five repositories (A.8.28)Extend coverage
OFI-09CCTV retention 30 days against 90 day policy (A.7.4)Align policy or storage
OFI-10Asset register coverage 94% (A.5.9)Reconcile with cloud inventory

6. DPDP Act readiness

The Digital Personal Data Protection Act, 2023 sets duties for a Data Fiduciary, rights for Data Principals and penalties administered by the Data Protection Board of India after inquiry. The Rules were notified in November 2025 with phased commencement; most operative duties, including security safeguards and breach intimation procedure, are scheduled to apply from May 2027. The practical advice is to build now, because consent, rights and breach processes take months to change.

ProvisionObligation (summary)Position foundStatusAction
s.4Lawful purpose: personal data may be processed only with consent or for certain legitimate usesPurpose register exists for lending and collections. Marketing purposes not separated.PartlySeparate marketing purpose and record lawful basis per purpose
s.5, Rule 3Notice: itemised description of data and purpose, with how to exercise rights and complainPrivacy notice published in English only. Does not list rights process or Board complaint route.PartlyUpdate notice; offer English or an Eighth Schedule language
s.6Consent: free, specific, informed, unconditional, unambiguous; withdrawal as easy as givingConsent captured as a bundled tick box at onboarding. No withdrawal flow in the mobile app.GapGranular consent, withdrawal in app and portal, consent log with version
s.7Certain legitimate uses (for example, voluntary provision, compliance with law)Legal basis for regulatory reporting and KYC retention documented.MetKeep register current
s.8(1), 8(2)Data Fiduciary is responsible for compliance, including for processing by a Data Processor under a valid contractProcessor list has 18 entries. 4 of 10 sampled contracts lack DPDP terms (see NC-05).PartlyContract schedule, annual processor review
s.8(3)Ensure completeness, accuracy and consistency where data is used to decide about the Data Principal or disclosedCorrection workflow for customer master data present; credit decisions use verified sources.MetEvidence sampling each year
s.8(4)Appropriate technical and organisational measures to ensure complianceISMS controls assessed in sections 3 and 4. Privacy governance has no owner outside IT.PartlyName a privacy owner and add DPDP to the ISMS risk method
s.8(5), Rule 6Reasonable security safeguards to prevent a personal data breachControls broadly strong (encryption, access control, MFA, logging). Gaps in log retention and restore testing.PartlyClose NC-03 and NC-04; confirm vendor log retention for Rule 6 expectations
s.8(6), Rule 7Intimate a personal data breach to the Board and affected Data Principals, in the prescribed form and mannerIncident plan covers CERT-In 6 hour reporting. No Board and Data Principal notification steps or templates.GapAdd breach assessment, notification templates and decision tree; tabletop
s.8(7), 8(8)Erase personal data when consent is withdrawn or the purpose is no longer served, unless law requires retention; ensure processors also eraseRetention schedule exists for 11 of 18 data categories. No automated deletion in lending data store.PartlyComplete retention schedule; deletion jobs; processor attestations
s.8(9)Publish business contact information of the DPO or a person able to answer Data PrincipalsGrievance email published on the website; person not named.PartlyPublish contact details of the named person
s.8(10), s.13Effective grievance redressal mechanism; right of grievance redressalComplaint handling exists for RBI Ombudsman matters; no DPDP-specific path or time-bound response.PartlyDefine DPDP grievance flow with response timeline
s.9Children: verifiable parental consent; no tracking or targeted advertising directed at childrenProducts are for adults. Age check at onboarding in place.MetDocument the age-gating decision
s.10, Rule 13Significant Data Fiduciary (if notified): DPO in India, independent data auditor, periodic impact assessmentNot notified at the date of the audit. Volume and sensitivity could qualify in future.CheckPrepare DPIA method and auditor shortlist in advance
s.11 to s.14Rights of Data Principals: access to information, correction and erasure, grievance, nominationAccess and correction handled through branch and email, no tracked workflow, no nomination option.GapBuild a rights request workflow with identity verification and SLA
s.16Transfer of personal data outside India permitted except to countries restricted by the GovernmentNo offshore processing identified. One SaaS tool hosts HR data in a non-India region.CheckConfirm hosting location and sectoral rules (RBI localisation expectations)

Readiness score: Met counts 1, Partly 0.5, Gap 0, over 14 assessable obligations = 50%. Items marked Check are excluded. The score is an internal planning aid, not a legal conclusion.

Penalty exposure (for planning)

FailureMaximum penalty under the Schedule
Failure to take reasonable security safeguards (section 8(5))Up to Rs 250 crore
Failure to give the Board and affected Data Principals notice of a personal data breach (section 8(6))Up to Rs 200 crore

Penalties are imposed by the Board after inquiry, considering factors listed in the Act. Other breaches carry separate ceilings in the Schedule.

Where ISO/IEC 27001 helps and where it does not

7. Certification-readiness verdict

Verdict: CONDITIONALLY READYThe ISMS is mature enough for external certification once the Major nonconformity and the SoA finding are closed and the team has one clean management review. We do not recommend booking Stage 2 until all five nonconformities are closed with evidence.
GateConditionStatusEarliest date
Gate 1: Stage 1 readyNC-01 and NC-02 closed. SoA v3.3 approved.OpenWeek 6 (mid December 2026)
Gate 2: Stage 2 readyNC-03, NC-04, NC-05 closed. Management review held with audit results as input.OpenWeek 12 (late January 2027)
Gate 3: DPDP foundationConsent, rights workflow and breach notification path designed and testedOpenBefore May 2027 commencement

What the certification body will do

Likelihood by area

Leadership and planning90%
Operation and controls80%
Evidence and records55%
Assurance (audit and review)40%
Privacy and DPDP50%

Likelihood values are the auditors' judgement of readiness at the audit date and are shown to help planning. They are not statistical measures.

8. Roadmap

WaveTimelineActionsOwner
10 to 30 daysNC-02 SoA review; NC-03 restore test; NC-04 retention and NTP; start NC-01 auditor appointmentsCISO, Head of IT
231 to 60 daysNC-01 audits completed; NC-05 supplier assessments and contract schedule; internal audit report to managementISMS manager, Procurement
361 to 90 daysDR failover test; management review with audit input; DPDP consent and rights designCISO, Compliance
490 to 120 daysBook certification body; DPDP breach notification tabletop; privacy owner appointedCISO, Compliance

Follow-up audit

After each nonconformity is reported closed, Virtual Caim performs a follow-up check of the evidence and issues a closure statement. For production-impacting controls, the check includes technical verification. The follow-up is scheduled by the Lead Auditor in agreement with the CISO.

Annex A. Evidence register

RefEvidenceRelated result
EV-01Context and interested parties registers v2.14.1, 4.2
EV-02ISMS scope statement and process map4.3, 4.4
EV-03Board minutes (Feb, Aug 2026)5.1, 9.3
EV-04Risk register export and method6.1.2
EV-05Statement of Applicability v3.26.1.3, NC-02
EV-06Internal audit programme and reports IA-2026-01 to 149.2, NC-01
EV-07Restore test and DR test recordsA.8.13, A.5.30, NC-03
EV-08SIEM retention report, NTP configuration extractsA.8.15, NC-04
EV-09Supplier register, assessments, contracts (10 sampled)A.5.19, NC-05
EV-10Privacy notice, consent forms, processor listDPDP s.5, s.6, s.8
EV-11Incident plan and tabletop report (April 2026)A.5.24, DPDP s.8(6)

Annex B. Glossary

TermMeaning
ISMSInformation security management system
SoAStatement of Applicability: list of Annex A controls, with inclusion, status and justification
NCNonconformity
OFIOpportunity for improvement
Data FiduciaryPerson who determines the purpose and means of processing personal data (DPDP Act)
Data PrincipalIndividual to whom the personal data relates
Data ProcessorPerson who processes personal data on behalf of a Data Fiduciary
DPBData Protection Board of India
SDFSignificant Data Fiduciary, notified by the Central Government
DPIAData protection impact assessment
RTO, RPORecovery time objective, recovery point objective
NIC, NPLNational Informatics Centre, National Physical Laboratory (time sources named in the CERT-In Directions)

Annex C. Sign-off

The report is signed by the auditors who conducted the audit, reviewed and signed by a designated reviewer who is not part of the audit team, and authorised by the head of the auditing organisation. Blocks are shown for format only. This sample carries no signatures.

Lead Auditor and auditors
Sample
Independent reviewer
Sample
Head of auditing organisation
Sample

All names, systems, evidence and results in this document are fictional. ISO and IEC standards are the property of their publishers.